Site activity log · Aug 2026 · All active projects

Today's Reports

3

of 3 active projects

Total Labor On-Site

91

Workers across all sites today

Active Projects

3

Expecting daily reports

Site Photos Today

26

Uploaded with reports

DPR Log

Report IDDateProjectWork SummaryLaborBottlenecksPhotosFiled ByStatusActions
dpr-00124/08/2026TodayRajesh Agarwal Residence

Completed 2nd floor slab shuttering. Reinforcement bars placed for columns C7-C12. Electrical conduit laying in progress on 1st floor.

28

Concrete pump delayed by 2 hrs due to traffic on NH-48.

6Sonu TiwariSubmitted
dpr-00224/08/2026TodaySunrise Pharma Office

False ceiling grid installation completed on floor 3. Cabin glass partition work 70% done. Electrical fixtures installation started floor 4.

18

Client requested change in cabin layout floor 4 — drawing revision pending.

8Bharti SharmaSubmitted
dpr-00324/08/2026TodayVikram Warehouse Complex

Block A column casting completed for grid 5-8. Block B pile cap excavation 60% done. PCC laying in progress.

45

Water shortage — tanker arranged at extra cost ₹4,500.

12Suresh PrajapatiReviewed
dpr-00423/08/2026Rajesh Agarwal Residence

Masonry work 1st floor — 40% complete. Plumbing rough-in for bathrooms 1 & 2 done.

24

4Sonu TiwariReviewed
dpr-00523/08/2026Vikram Warehouse Complex

Block A — RCC beam casting completed. Curing in progress. Site leveling work for parking area started.

42

One JCB breakdown — maintenance requested.

9TariqReviewed
dpr-00622/08/2026Sunrise Pharma Office

Floor 2 modular workstation installation complete. Carpet tiles laid in conference room. Fire alarm wiring started.

15

Fire NOC inspection scheduled for 26 Aug — site to be prepared.

7Bharti SharmaReviewed
Showing 6 of 6 reports · Click any row to expand details