| dpr-001 | 24/08/2026Today | Rajesh Agarwal Residence | Completed 2nd floor slab shuttering. Reinforcement bars placed for columns C7-C12. Electrical conduit laying in progress on 1st floor. | 28 | Concrete pump delayed by 2 hrs due to traffic on NH-48. | 6 | Sonu Tiwari | Submitted | |
| dpr-002 | 24/08/2026Today | Sunrise Pharma Office | False ceiling grid installation completed on floor 3. Cabin glass partition work 70% done. Electrical fixtures installation started floor 4. | 18 | Client requested change in cabin layout floor 4 — drawing revision pending. | 8 | Bharti Sharma | Submitted | |
| dpr-003 | 24/08/2026Today | Vikram Warehouse Complex | Block A column casting completed for grid 5-8. Block B pile cap excavation 60% done. PCC laying in progress. | 45 | Water shortage — tanker arranged at extra cost ₹4,500. | 12 | Suresh Prajapati | Reviewed | |
| dpr-004 | 23/08/2026 | Rajesh Agarwal Residence | Masonry work 1st floor — 40% complete. Plumbing rough-in for bathrooms 1 & 2 done. | 24 | — | 4 | Sonu Tiwari | Reviewed | |
| dpr-005 | 23/08/2026 | Vikram Warehouse Complex | Block A — RCC beam casting completed. Curing in progress. Site leveling work for parking area started. | 42 | One JCB breakdown — maintenance requested. | 9 | Tariq | Reviewed | |
| dpr-006 | 22/08/2026 | Sunrise Pharma Office | Floor 2 modular workstation installation complete. Carpet tiles laid in conference room. Fire alarm wiring started. | 15 | Fire NOC inspection scheduled for 26 Aug — site to be prepared. | 7 | Bharti Sharma | Reviewed | |